SAN BERNARDINO (AP) – Work on a massive solar energy project could be delayed because several pairs of red-tailed hawks are nesting in the path of a power line.
The Riverside Press-Enterprise reports Sunday that Southern California Edison crews have been trying to upgrade a transmission line in the Mojave Desert to connect the solar project to the power grid.
The Bureau of Land Management said work on the line was expected to be done this month, but crews won’t be able to complete it until after the hawk nesting season ends in August.
A spokesman for BrightSource Energy Co. says that won’t delay the company’s plans to begin delivering electricity early next year from the solar plant.
(© Copyright 2012 The Associated Press. All Rights Reserved. This material may not be published, broadcast, rewritten or redistributed.)





Baseball Shots Of The Week –...
Best Summer Dishes
CBS 2013-2014 Prime Time Shows
Flash Forward: Concept Cars...
Baseball Shots Of The Week –...
Big Screen to Broadway: Movie...
Broadway Posters
Best Summer Festivals and...
Baseball Shots Of The Week –...
Grass Fire In Glendale Forces...
Springs Fire In Camarillo
Summit Fire
Best Mexican Cuisine
Celebrities With Asthma
Baseball Shots Of The Week –...
Best Wedding Dress Styles For...